Progress Update
/Phase III mezzanines are going in!
Phase III mezzanines are going in!
Early March drone pictures. Thanks to Better Buildings, Inc.
The doors and windows have been installed and the stucco has been completed. The plumbing, electric and fire sprinkler subcontractors are finishing up.
Up next? Drywall.
The roof is up on building three.
The roof panels for Phase III building one are being installed.
The concrete for Phase III building two is being poured.
Limited to just 499 Ferrari collectors and only 150 in the United States, this 458 Speciale A patiently awaits it's new home at My Other Place.
The Butler steel structure for the north building of Phase II has been erected. Exterior wall panels are on the way. Steel erection crews are currently working on the south building, which will take approximately seven days to complete.
Both the North and South building slabs have been poured. Close to 1200 tons of concrete used!
Now just a few days of curing before the steel erection starts.